THE number of trains running between Harrogate and York is set to double after council chiefs pledged to spend £13m on rail upgrades.

North Yorkshire County Council has approved funds for improvement works, which will see a twice-hourly service introduced in both directions by May 2021.

The train tracks are currently running using centuries-old technology – and funds for the long-awaited improvement project were first secured in 2013.

Cllr Don Mackenzie, executive member for access, said: “One train running every hour in each direction is simply not good enough.

“This rail scheme has been on the books for as long as I have been an executive member – and clearly we want to make sure rail services between Harrogate and York are improved.

“Any improvements for rail services is always good news, but especially for a town and city which are so reliant on tourism.”

The plans were approved at a virtual meeting.

The county council thought it would require an almost full doubling of the track at a cost of more than £40million.

Objections were also raised by train operators using the connecting east coast main line. They argued more frequent trains between Harrogate and York would affect their services.

And there were more questions hanging over the project when the government stripped troubled rail operator Northern of its franchise.

However, following an investigation with Network Rail, an affordable scheme was identified, involving limited track improvements and signalling upgrades, and work is now expected to start in summer.

The main improvement will involve upgrading the token block signalling to more modern technology.

Other improvement works will also allow faster speeds and more efficient use of a length of double track at Cattal.

A total of £9.6million of the scheme’s budget is being provided by York, North Yorkshire and East Riding Enterprise Partnership.

North Yorkshire County Council will use £3.4million in parking fines to pay for the rest.